🏠 Residential 🏗 Civil 🏢 Commercial
A
ARCUS
ENGINEERING · ARCHITECTURE · INTERIORS
Civil & Construction
Select Property Type
🏡
Residential
House / Villa
🏗
Commercial
Building
🏭
Industrial
Factory / Shed
Admin password  |  or registered mobile (Customer)
Project Information
Step 1 of 12 — ARCUS Civil & Structural Estimator V1
Civil & Structural V1
📋
Client & Project Details
01
🔗 Link to ARCUS Estimator (optional)
Link civil works to an existing Commercial Interiors estimate for unified BOQ
Auto-pulled when platform is live. Enter manually for now.
🏗
Building Details
02
Floor-wise Built-up Area (BUA)
Floor BUA (sq.ft) * Carpet Area (sq.ft)
TOTAL BUA 0 sq.ft
Used for perimeter → barricading & green net calculation
Drives water tanker, site office & safety provisions on Page 3
⚙️
Structural Parameters
03
Typical bay size. Extracted from structural drawing if uploaded.
Current TMT bar rate at site. Updates material cost.
📝
Scope & Exclusions
04
Contractual Terms
Determines how contractor is paid — lump sum is most common for private projects
Protects both parties when steel/cement prices fluctuate during construction
Penalty for contractor delay — typically 0.5–1% of contract value per week, max 10%
Dispute resolution forum — should match project location
CAR + WC is standard for all civil contracts above ₹10 lakhs
Amount withheld until DLP completion — security against defects
Select Floor to Analyze:
Set No. of Floors in Project Info. Each floor plan is analyzed separately and quantities are merged.
📐
Upload Floor Plan
Claude reads: room labels, dimensions, column grid, wall lengths, openings, BUA per zone
JPGPNG PDFWEBP
Analysing Drawing...
  • 1
    Uploading drawing
  • 2
    Identifying drawing type & scale
  • 3
    Extracting dimensions & quantities
  • 4
    Building quantity take-off
📋 Manual Quantity Entry (if drawing not available)
Estimation Mode
📐 Detailed Estimate: Enter zone/location-wise measurements manually (per MB format).
Building Use
Plot Area
Foundation
Earthwork Total
₹ 0
🌿
Site Clearance & Demolition
Jungle/shrub clearing, demolition of existing structure, stump removal, debris disposal
₹ 0
🚜
Bulk Excavation
Mass earthwork, basement excavation (cum) — mechanised
₹ 0
Trench Excavation
Foundation trenches, column pits, drain trenches — manual + machine
₹ 0
🔨
Backfilling & Compaction
Earth backfill, sand filling, gravel filling, mechanical compaction (cum)
₹ 0
🚛
Disposal of Excavated Earth
Carting away surplus earth, tipping charges, lorry hire
₹ 0
🛡
Anti-termite Treatment
Pre-construction chemical treatment — soil poisoning, perimeter, column pits
₹ 0
🪨
Soling, Levelling & Grading
Rubble soling, sand layer, site grading, temporary road, site levelling
₹ 0
🟢
Site Safety & Pollution Control
Green shade net · Polypropylene cover · Dust suppression · Barricading · CPCB compliance Statutory
₹ 0
📐 Auto-population from Page 1
🔹 Green net area = Plot perimeter × Building height
Page 1 → Plot Area + No. of Floors + Floor Height
🔹 Barricading = Plot perimeter (√Plot × 4)
Page 1 → Plot Area (sq.ft)
🔹 Water tanker months = Construction duration
Page 1 → Construction Duration (months) ★
🔹 Signage count = 1 board per 50 rft perimeter
Page 1 → Plot Area (auto-calculated)
⚠️ Fill Plot Area and Construction Duration on Page 1 before navigating to Page 3 for correct auto-population.
📋 Statutory Requirement — As per CPCB guidelines and municipal building bylaws (GHMC/BMC/BDA), all buildings under construction must be covered with green shade net or polypropylene sheets to prevent dust and debris from spreading. Barricading is mandatory for all sites abutting public roads.
📊
Earthwork Summary
A — Earthwork
TradeItem Description Qty Unit Rate (₹) Amount (₹)
Fill in earthwork items above to see summary
Foundation Type
Concrete Grade
Columns
Foundation Total
₹ 0
Live rates from Page 1:  Steel @ ₹72/kg  |  Cement @ ₹450/bag  |  Grade: — (select on Page 1)  |  Depth: 5 ft Update rates on Page 1 → they reflect here automatically
🪨
PCC — Plain Cement Concrete
M10 blinding / levelling course under all footings & slabs
₹ 0
🏗
RCC Footings
Isolated / combined / strip / raft — concrete + shuttering + reinforcement (all-in per cum)
₹ 0
⬇️
Pile Foundation
Bored cast-in-situ, driven precast, pile cap, ground beam
₹ 0
🔩
Column Starters & Pedestals
RCC starters from footing top to plinth level — per nos / per cum
₹ 0
💧
Foundation Waterproofing
Bituminous coating, crystalline admixture, torch-applied membrane to footing faces
₹ 0
🏗
Scaffolding — Foundation Stage
Scaffolding for foundation works — excavation support, formwork access, pile cap works
₹ 0
📊
Foundation Summary
Section B
Sub-headItem Description Qty Unit Rate (₹) Amount (₹)
Fill foundation items above to see summary
BUA
Floors
System
Conv. RCC
RCC Total
₹ 0
Select Structural System
🏗
Conventional RCC
M25/M30 columns, beams, slabs
Shuttering + rebar (Fe500)
🔧
Post-Tensioned (PT)
PT slabs + PT beams
Conventional columns
🏭
Precast
Precast columns, beams
Hollow Core / Double Tee slabs
Steel @ ₹72/kg  |  Cement @ ₹450/bag
🏛
RCC Columns
All floors — concrete + formwork + reinforcement — all-in per cum
₹ 0
RCC Beams
Primary, secondary, lintel, plinth beams — all-in per cum
₹ 0
RCC Slabs
Floor slab, roof slab, terrace slab — all-in per sq.ft
₹ 0
🪜
Staircases & Lift Pit
Dog-legged staircase per flight, lift pit RCC
₹ 0
🧱
Parapet, Chajja & Lintels
Parapet wall, chajja, window sill, lintel, coping, loft slab
₹ 0
🏛
Shear Walls & Core Walls
RCC shear walls, coupling beams, lift core / elevator shaft walls
₹ 0
🪨
RCC Retaining Walls
Cantilever, counterfort, basement retaining walls, breast walls, shear key
₹ 0
🚰
Underground Sumps
RCC UG sump walls, floor slab, cover slab, waterproofing, accessories
₹ 0
🏗
Overhead Water Tanks (OHT)
RCC OHT — circular/rectangular, staging columns, waterproofing, accessories
₹ 0
🛗
Lift Core & Elevator Shaft
Lift core walls, pit slab, machine room slab, guide rail embedments
₹ 0
⚙️
Miscellaneous RCC
Ground floor slab, sunken slab, ramp, swimming pool, septic tank, road
₹ 0
🏗
Scaffolding — RCC Stage
Scaffolding for RCC works — columns, beams, slabs, staircase formwork access
₹ 0
Conventional RCC Summary
📊
RCC Works Summary
Section C — Conventional RCC
Sub-headItem Description Qty Unit Rate (₹) Amount (₹)
Fill RCC items above to see summary
Ext. Wall (rft)
Int. Wall (rft)
Floors
Masonry Total
₹ 0
Floor-to-floor less beam/slab
🧱
External / Perimeter Walls
Outer skin — 230mm / 200mm thick, all floors
₹ 0
🔲
Internal Partition Walls
Room partitions — 115mm / 100mm thick, all floors
₹ 0
Lintels, Sill Bands & Fillets
RCC / brick lintel over openings, sill course, DPC
₹ 0
🏠
Compound Wall & Gate
Boundary wall, coping, RCC pillars, gate frames
₹ 0
🪨
Miscellaneous Masonry
Brick bat coba, DPC, filler slab, step masonry
₹ 0
🏗
Scaffolding
External & internal scaffolding for masonry works · incl. loading, shifting, dismantling, transport
₹ 0
Rate structure: 1st month ₹12/sq.ft · 2nd month ₹10/sq.ft · 3rd month onwards ₹8/sq.ft
Includes: loading, laying, shifting, dismantling & transport. Measurement = scaffold area (sq.ft) × months.
📊
Masonry Summary
Section D
Sub-headItem Description Qty Unit Rate (₹) Amount (₹)
Fill masonry items above to see summary
Int. Wall Area
Ext. Wall Area
Plastering Type
Cement
Plastering Total
₹ 0
🖌
Internal Plaster
12mm cement plaster 1:4, two coats, smooth finish — walls & ceilings
₹ 0
🏢
External Plaster
20mm cement plaster 1:4, roughcast / textured finish, weather coat
₹ 0
🏗
Scaffolding
External & internal scaffolding for plastering works
₹ 0
Rate structure: 1st month ₹12/sq.ft · 2nd month ₹10/sq.ft · 3rd month onwards ₹8/sq.ft
Includes: loading, laying, shifting, dismantling & transport. Measurement = scaffold area (sq.ft) × months.
💧
Waterproof Plaster
Integral WP compound — bathrooms, kitchen, terrace parapet, sump walls
₹ 0
Gypsum Plaster & Putty
Machine-applied gypsum, undercoat + finish coat, wall putty / skim coat
₹ 0
🎨
Texture & Speciality Finishes
Sand face, sponge finish, textured paint base, Tyrolean, roughcast
₹ 0
📊
Plastering Summary
Section E
Sub-headItem Description Qty Unit Rate (₹) Amount (₹)
Fill plastering items above to see summary
Terrace Area
Basement Area
WP System
Torch-applied
WP Total
₹ 0
🏠
Terrace / Roof Waterproofing
Roof slab — membrane + insulation + screed + protection course
₹ 0
⬇️
Basement Tanking
External tanking, internal tanking, drainage cell, dimple mat, cavity drain
₹ 0
🚰
Sump, UGT & Wet Areas
Underground water tank, sump pit, toilet WP, lift pit, planter box
₹ 0
↔️
Expansion Joints & Miscellaneous
Expansion joint sealing, crack injection, epoxy grouting, movement joints
₹ 0
📊
Waterproofing Summary
Section F
Sub-headItemQtyUnitRate (₹)Amount (₹)
Fill waterproofing items above
Façade Area
Glazing Area
Glazing System
SSG
Façade Total
₹ 0
🪟
Structural Glazing & Curtain Wall
SSG, spider, curtain wall, unitised, point fixed — per sq.ft installed
₹ 0
🏢
External Cladding
ACP, HPL, GRC, stone, terracotta, brick slip, metal panel — per sq.ft
₹ 0
🚪
External Doors & Windows
Aluminium windows, UPVC, entrance doors, automatic sliding doors
₹ 0
Canopy, Sunshade & Projections
MS/glass canopy, RCC chajja, parapet coping, louvres, fins
₹ 0
🎨
External Paint & Sealants
Exterior emulsion, elastomeric coating, masonry paint, anti-fungal
₹ 0
📊
Elevation & Façade Summary
Section G
Sub-headItemQtyUnitRate (₹)Amount (₹)
Fill façade items above
🏗
Scaffolding
External scaffolding for facade & elevation works
₹ 0
Rate structure: 1st month ₹12/sq.ft · 2nd month ₹10/sq.ft · 3rd month onwards ₹8/sq.ft
Includes: loading, laying, shifting, dismantling & transport. Measurement = scaffold area (sq.ft) × months.
Estimation Mode
📐 Detailed Estimate: Enter road lengths, drain lengths, areas element-wise. Accuracy ±5%.
A — Roads & Pavements
🚧
Road Formation
Sub-grade preparation, embankment, GSB, WBM, WMM, prime coat, tack coat
₹ 0
🛣
Road Surface Course
BM, DBM, bituminous concrete, PCC road, paver blocks, cobblestone, interlocking tiles
₹ 0
🪨
Kerb, Edge & Speed Control
Precast kerb, granite kerb, concrete edging, speed breakers, wheel guards
₹ 0
🚦
Road Markings & Signage
Thermoplastic markings, parking bays, sign boards, cat eyes, delineators
₹ 0
B — Storm Water Drainage
🌊
Drain Structures & Pipes
RCC box drains, precast U-drains, brick drains, HDPE pipe, hume pipe
₹ 0
🕳
Manholes, Chambers & Gratings
RCC / brick manholes, catch basins, gully traps, CI gratings, manhole covers
₹ 0
⚙️
Drainage Miscellaneous
Outfall headwall, silt trap, oil interceptor, retention pond lining, trench excavation
₹ 0
C — Water Supply & Distribution
🚰
Water Supply Pipelines & Fittings
HDPE / GI / uPVC pipes, sluice valves, air valves, fire hydrant, water meter
₹ 0
D — Site Development
🧱
Compound Wall & Fencing
Brick / precast compound wall, MS railing, chainlink, gate pillars, main gate
₹ 0
🌿
Landscaping & Horticulture
Topsoil, lawn, garden paving, stepping stones, drip irrigation, plantation
₹ 0
💡
External Lighting
Street light poles, LED lights, garden lights, underground cables
₹ 0
🅿
Parking
Paver block / concrete parking bays, bay markings, wheel stops, speed humps
₹ 0
Estimation Mode
📐 Detailed Estimate: Enter member-wise measurements (per rmt, per MT) manually.
Steel Rate
₹68/kg
Est. Tonnage
Fabrication Grade
Heavy
Steel Total
₹ 0
Live steel @ ₹68/kg  |  IS 2062 Grade E250
🔩
Structural Steel Frame
MS columns, primary beams, base plates, connections, anchor bolts — per MT supply + fab + erect
₹ 0
🔺
Roof Trusses & Purlins
MS roof truss, Z/C purlins, bracing, ridge, GI/aluminium roofing sheet
₹ 0
🪜
Steel Staircase & Handrails
MS open-riser staircase, SS handrail, glass railing, balustrade — per flight / rmt
₹ 0
Miscellaneous Fabrication
Grating, cat ladder, sunshade frame, pergola, anchor bolts, MS grille
₹ 0
📊
Structural Steel Summary
Section H
Sub-headItemQtyUnitRate (₹)Amount (₹)
Fill steel items above
Civil Works
₹ 0
Commercial Interiors
₹ 0
Combined Total
₹ 0
Net Payable
₹ 0
📋
Abstract of Cost — Civil & Structural
Sec. Trade / Sub-head Amount (₹) Cost / sq.ft
Click "Refresh BOQ" to compile all sections
💼
Consultant Markup & Contingency
🔗
Link — ARCUS Interiors Estimator
No interiors estimator linked. Enter totals on Page 1 to show combined project estimate.
Pull from ARCUS Commercial V1 → Page 14 → Net Payable before GST
Pull from ARCUS Residential V1 → BOQ → Net Payable before GST
Statutory Levies
DescriptionBasisRateAmount (₹)
Civil Works Sub-totalAll sections A–H₹ 0
Contractor OH & ProfitOn sub-total12%₹ 0
Contingency & ProvisionalOn sub-total5%₹ 0
Grand Total (Civil)₹ 0
GST on Civil WorksOn Grand Total (Civil)18%₹ 0
BOCW Welfare CessBuilding & Other Construction Workers Welfare Cess Act, 19961%₹ 0
TDS (Sec 194C)On contract value2%₹ 0
NET PAYABLE (Civil)Grand Total + GST − TDS₹ 0
📐
Cost Benchmarks
Civil Cost / sq.ft BUA
₹ —
Structure Cost / sq.ft
₹ —
Combined Cost / sq.ft
₹ —
Total BUA
— sq.ft